Create New Metric Import Task
Use this wizard to create a new task to import
data into Metric Studio.
Procedure
- In IBM® Cognos® Connection, click the new data integration task button on the toolbar, and then click New metric import from files.
- Type the name and description to represent this new import task and if necessary, change the location to place the task, and click Next.
- Click the Transfer data from staging area into metric store to change the pre- and post- import options for the task. Click the options you want to use when the task is run. Click Next.
- Select the action you want:
- To run now or later, click Save and run once and click Finish. Specify the time and date for the run. Then click Run. Review the run time and click OK.
- To schedule at a recurring time, click Save and schedule and
click Finish. Then, select frequency and start
and end dates. Then click OK.
Tip: To temporarily disable the schedule, select the Disable the schedule check box. To view the schedule status, see Manage Scheduled Activities.
- To save without scheduling or running, click Save only then click Finish.